You can associate calendars with Activities (using the CALID variable in the Activity data set) or Resources (using observations with the keyword CALENDAR for the OBSTYPE= variable in the Resource data set).
PROC CPM enables you to define very general calendars using the WORKDATA, CALEDATA, and HOLIDATA data sets and options in the PROC CPM statement. Recall that these data sets are referred to as the Workday, Calendar, and Holiday data sets, respectively. The Workday data set specifies distinct shift patterns during a day. The Calendar data set specifies a typical work week for any given calendar; for each day of a typical week, it specifies the shift pattern that is followed. The Holiday data set specifies a list of holidays and the calendars that they refer to; holidays are defined either by specifying the start of the holiday and its duration in interval units, or by specifying the start and end of the holiday period. The Activity data set (the DATA= input data set) then specifies the calendar that is used by each activity in the project through the CALID variable (or a default variable _CAL_). Each of the three data sets used to define calendars is described in greater detail later in this section. Each new value for the CALID variable in either the Calendar data set or the Holiday data set defines a new calendar. If a calendar value appears in the Calendar data set and not in the Holiday data set, it is assumed to have the same holidays as the default calendar (the default calendar is defined later in this section). If a calendar value appears in the Holiday data set and not in the Calendar data set, it is assumed to have the same work pattern structures (for each week and within each day) as the default calendar. In the Activity data set, valid values for the CALID variable are those that are defined in either the Calendar data set or the Holiday data set.
If there is no CALID variable and no Calendar and Workday data sets, the default calendar is defined by interval and the DAYSTART= and DAYLENGTH= options in the PROC CPM statement. If interval is DAY, DTDAY, DTHOUR, DTMINUTE or DTSECOND, work is done on all seven days of the week; otherwise, Saturday and Sunday are considered to be nonworking days. Further, if the schedule is computed as SAS datetime values, the length of the working day is determined by daystart and daylength. All of the holidays specified in the Holiday data set refer to this default calendar, and all of the activities in the project follow it. Thus, if there is no CALID variable, the default calendar is the only calendar that is used for all of the activities in the project.
If there is a CALID variable that identifies distinct calendars, you can use an observation in the Calendar data set to define the work week structure for the default calendar. Use the value `0' (if CALID is a numeric variable) or the value `DEFAULT' (if CALID is a character variable) to identify the default calendar. In the absence of such an observation, the default calendar is defined by interval, daystart, and daylength, as described earlier. The default calendar is used to substitute default work patterns for missing values in the Calendar data set or to set default work week structures for newly defined calendars in the Holiday data set.
All numeric variables in the Workday data set are assumed to denote unique shift patterns during one working day. For each variable the observations specify, alternately, the times when consecutive shifts start and end. Suppose S1, S2, and S3 are numeric variables formatted as TIME6. Consider the following Workday data:
S1 S2 S3
7:00 . 7:00 (start)
11:00 08:00 11:00 (end)
12:00 . . (start)
16:00 . . (end)
The variables S1, S2, and S3 define three different work patterns. A missing value in the first observation is assumed to be 0 (or 12:00 midnight); a missing value in any other observation is assumed to denote 24:00 and ends the definition of the shift. Thus, the workdays defined are:
The last two values for the variables S2 and S3 (both values are `24:00', by default) are ignored. This data set can be used to define all of the unique shift patterns that occur in any of the calendars in the project. These shift patterns are tied to the different calendars in which they occur using the Calendar data set.
The Calendar data set defines specific calendars using the names of the shift variables in the Workday data set. Use the variable specified in the CALID statement or a variable named _CAL_ to identify the calendar name or number. Character variables named _SUN_, _MON_, _TUE_, _WED_, _THU_, _FRI_, and _SAT_ are used to indicate the work pattern that is followed on each day of the week. Valid values for these variables are `HOLIDAY', `WORKDAY' or, any shift variable name defined in the Workday data set.
Note: A missing value for any of these variables is assumed to denote that the work pattern for the corresponding day is the same as for the default calendar.
When interval is specified as DTDAY, WORKDAY, or DTWRKDAY, it is necessary to know the length of a standard working day in order to be able to compute the schedules consistently. For example, a given calendar may have an eight-hour day on Monday, Tuesday, and Wednesday and a seven-hour day on Thursday and Friday. If a given activity following that calendar has a duration of four days, does it mean that its duration is equal to 8×4 = 32 hours or 7×4 = 28 hours? To avoid ambiguity, a numeric variable named D_LENGTH can be specified in the Calendar data set to define the length of a standard working day for the specified calendar. If this variable is not found in the Calendar data set, all calendars for the project are assumed to have a standard daylength as defined by the default calendar.
For example, consider the following Calendar data:
_CAL_ _SUN_ _MON_ _TUE_ _FRI_ _SAT_ D_LENGTH
1 HOLIDAY S1 S1 S2 S3 8:00
2 HOLIDAY . . . HOLIDAY .
3 . . . . . .
These three observations define three calendars: `1', `2', and `3'. The values `S1', `S2', and `S3' refer to the shift variables defined in the "WORKDATA Data Set" section. Activities in the project can follow either of these three calendars or the default calendar.
Suppose daystart has been specified as 9:00 a.m. and daylength is eight hours. Further, suppose that interval is DTDAY. Using these parameter specifications, PROC CPM defines the default calendar and calendars 1, 2 and 3 using the Calendar data set just defined:
The HOLIDATA data set (referred to as the Holiday data set) defines holidays for the different calendars that may be used in the project. Holidays are specified by using the HOLIDAY statement. See the HOLIDAY statement earlier in this chapter for a description of the syntax. This data set must contain a variable (the HOLIDAY variable) whose values specify the start of each holiday. Optionally, the data set may also contain a variable (the HOLIDUR variable) used to specify the length of each holiday or another variable (the HOLIFIN variable) specifying the finish time of each holiday. The variable specified by the CALID statement (or a variable named _CAL_) can be used in this data set to identify the calendar to which each holiday refers. A missing value for the HOLIDAY variable in an observation causes that observation to be ignored. If both the HOLIDUR and the HOLIFIN variables have missing values in a given observation, the holiday is assumed to start at the date and time specified for the HOLIDAY variable and last one unit of interval where the INTERVAL= option has been specified as interval. If a given observation has valid values for both the HOLIDUR and the HOLIFIN variables, only the HOLIFIN variable is used so that the holiday is assumed to start and end as specified by the HOLIDAY and HOLIFIN variables, respectively. A missing value for the CALID variable causes the holiday to be included in all of the calendars, including the default.
The HOLIDUR variable is a natural way of expressing vacation times as n workdays, and the HOLIFIN variable is more useful for defining standard holiday periods, such as the CHRISTMAS holiday from 23DEC87 to 25DEC87 (both days inclusive). Note that the HOLIDUR variable is assumed to be in units of interval and the procedure uses the particular work pattern structure for the given calendar to compute the length (finish time) of the holiday.
For example, consider the following Holiday data:
HOLISTA HOLIDUR HOLIFIN _CAL_
23DEC87 . 25DEC87 .
01JAN88 1 . 1
18JAN88 . . 2
28JAN88 3 . 2
28JAN88 3 . 3
Suppose calendars `1', `2', and `3' and the default calendar have been defined as described earlier in the description of the Calendar and Workday data sets. Recall that in this example INTERVAL=DTDAY, DAYSTART='09:00'T, and DAYLENGTH='08:00'T. Because the schedule is computed as SAS datetime values (since INTERVAL=DTDAY), the holiday values (specified here as SAS date values) are converted to SAS datetime values. The first observation in the Holiday data set has a missing value for _CAL_ and, hence, the holiday in this observation pertains to all the calendars. As defined by the Holiday data, the holiday lists for the different calendars (not including breaks due to shift definitions) are as shown in Table 2.23.
Note that, even though both calendars `2' and `3' have the same specifications for HOLISTA and HOLIDUR, the actual holiday periods are different for the two calendars. For calendar `2', the three days starting from Thursday, January 28, imply that the holidays are on Thursday, Friday, and Monday (because Saturday and Sunday are already holidays). For calendar `3' (all seven days are working days), the holidays are on Thursday, Friday, and Saturday.
Table 2.23: Holiday Definitions| Calendar | Holiday Start | Holiday End |
|---|---|---|
| 0 | 23DEC87:09:00 | 25DEC87:16:59:59 |
| 1 | 23DEC87:09:00 | 25DEC87:07:59:59 |
| 01JAN88:00:00 | 01JAN88:07:59:59 | |
| 2 | 23DEC87:09:00 | 25DEC87:16:59:59 |
| 18JAN88:09:00 | 18JAN88:16:59:59 | |
| 28JAN88:09:00 | 01FEB88:16:59:59 | |
| 3 | 23DEC87:09:00 | 25DEC87:16:59:59 |
| 28JAN88:09:00 | 30JAN88:16:59:59 |
You can use the GANTT procedure to visualize the breaks and holidays for the different calendar. Figure 2.4 shows all the breaks and holidays for the period between Christmas and New Year. Holidays and breaks are denoted by *. Likewise, Figure 2.5 shows the vacation periods in January for calendars `2' and `3'.
|
|
|
Chapter Contents |